Mixed-utility reconstruction for Logan City, delivered on schedule with multiple subcontractors and live engineering coordination.

Project detail

The work,
in detail.

ClientLogan City
LocationLogan, UT
Year2024
RoleGeneral contractor
Duration~5 months
Contract value~$1.2M
StatusDelivered on schedule

Scope of work

  • ~3,800 LF water main replacement (8–12 in. PVC C900)
  • Sanitary sewer rehabilitation with new service laterals
  • Storm drain inlets, conveyance pipe, and outfall
  • Full roadway section and surface restoration
  • Resident access maintained throughout construction

On the job

Temple Heights was a full corridor reconstruction for Logan City: aging water, sewer, and storm utilities replaced under a single contract while keeping the street open to the people who live on it.

We ran the critical path with our own crews and coordinated several specialty subs, holding weekly engineering reviews with the City. Daily logs, testing records, and inspection sign-offs were submitted as the work happened, and the job closed out on schedule with no outstanding punch items.

On site

From the jobsite.

Temple Heights project site — jobsite photo
Temple Heights project site — utility installation
Got a job

Does your project look like these?

Send us the plans and a deadline. If it’s a job for our crew, we’ll have a clean number back on your timeline.